Sauk Valley Community College HVAC Upgrades

Total Project Cost: $2,743,000

Strong Values, Customer Oriented, We Deliver

Project #: 211124A
Project Type: Institutional
Owner: State of Illinois, SVCC
Client: Valdes Engineering and Architecture
Sq Footage: 62,930
Project Description:

SVCC has been undertaking air handling unit replacement projects over the last several years. This project included replacement of the final five AHU’s and replacement of the main Cooling Tower. The AHU’s included Steam F&B coils and chilled water coils. A laser scan and point cloud were generated to ensure the new equipment would fit inside the existing mechanical rooms. Shut-downs and equipment installation had to be carefully coordinated with the facility. Our deliverables included DD, 50% IFR and 95% IFA/IFB with 100% IFC Drawing sets and specifications. Our firm also provided full CA services for this project including Site Observation Reporting, Punch List Reporting and assisted with Start-up and Cx.

Project History

#
$
December 29, 2021

Contracted On

October 28, 2022

Design Completed

December 15, 2022

Construction Began

September 10, 2024

Construction Completed