Keasbey Facility, Hard Seltzer Process Addition
Total Project Cost: $3,500,000
Strong Values, Customer Oriented, We Deliver

This project included new storage vessels which required jacket cooling for normal process usage and during product unloading. Glycol solution was transferred from the existing CUB to a break heat exchanger and pumping system. This project included a design study of the existing Glycol Chiller system to ensure adequate capacity was available for this project. Deliverables included complete design documents with P&ID’s, CA Services and full Commissioning Services. All of the PLC controls were furnished, installed and programmed by a third party, D/B partner. This project included a full scan of the facility to identify pipe routing from the CUB to the newly renovated space. Piping spool drawings were developed for this project.
Project History