Oterra Warehouse HVAC Study and Phase 3 Renovation

Total Project Cost: $575,000

Strong Values, Customer Oriented, We Deliver

Project #: 230901A,B
Project Type: Commercial
Owner: Oterra
Client: Valdes Engineering and Architecture
Sq Footage: 42,147
Project Description:

Performed HVAC study of cGMP warehouse and office to determine viability of reusing existing equipment for renovation. New plumbing to support installation of Owner provided coolers and freezers for cGMP storage of pharmaceutical products. My firm worked with Valdes Architecture and Engineering, Inc. to complete the project surveys, develop the HVAC system study and design plumbing/drainage systems to support Owner provided equipment. Deliverables included Narrative and project drawings with written specifications for the plumbing design. Deliverables also included the Permit Set, 100% IFC Construction Documents. My firm is also providing full Construction Administration for this project.

Project History

#
$
October 3, 2023

Contracted On

December 6, 2023

Design Completed

April 18, 2024

Construction Began

March 13, 2025

Construction Completed